Set up for a progress claim. Keep the stage you're claiming, enter the amount, and save it as a PDF. Free, and nothing leaves your device.
Bill to
| Description | Qty | Price | Amount |
|---|
For domestic building contracts in Victoria, Consumer Affairs Victoria sets the most you can claim at each stage. For a contract covering all stages: base 10%, frame 15%, lock-up 35% and fixing 25% of the contract price. For a contract to lock-up only: base 20% and frame 25%. For a contract to fixing: base 12%, frame 18% and lock-up 40%. Claim a stage only once it's complete.
The deposit is capped too: 10% if the contract price is under $20,000, and 5% if it's $20,000 or more.
Each claim should say which contract it's under, which stage it's for, and that the stage is complete. Approved variations go on their own lines so the customer can match them to the signed variation.
Other states set their own progress payment rules. Check your state's consumer affairs or building regulator before you rely on these numbers.
The starting lines are examples with no prices: add your own rates. Rules checked October 2026; they can change, so check your state's regulator for anything that matters.
Job management apps send quotes from your phone, turn them into invoices, chase late payers and sync with Xero or MYOB. See what ServiceM8, Tradify and Fergus would cost for your team.
Tell us what's eating your evenings (quotes, invoices, chasing payments, the BAS) and we'll match you with a bookkeeper or admin assistant who works with trades. Free to ask, no obligation.
Not under a Victorian domestic building contract: a stage payment is due only once that stage is complete.
Approved variations can be claimed with the stage, each on its own line with its variation number, so the customer can see what they're paying for.
If you're registered for GST, choose a GST option and the builder titles it TAX INVOICE with GST shown, which is what your customer needs.